Perspectives

Many of us believe we have excess capacity in Indian power sector. We see the numbers – installed capacity of 377 GW and think peak load is only 183 GW, we have too much capacity. Capacity utilisation (PLF) is only 50-60 % for most coal power plants, so first let them get to higher capacity utilisation. But when we look in detail, there can be peak power deficit, and hence there can be blackouts in some regions.

Situation Report

This article presents few of the examples from audit report of accounts and records of Central Government Companies and Corporations conducted by the officers of the Comptroller and Auditor General of India. Issues in NLC, IIFCL, BHEL, ONGC, HCL, DVC, MECON, SAIL are given.